MTCC has completed 75 percent of the canal dredging and outer canal laying project at N. Manadhoo port.
MTCC said the ramp construction and rivetment work has also been completed under the project.
Under the Manadhoo Port Project, 14,844 cubic meters of port will be dredged and 15,822 cubic meters of canal access will be dredged. A 175-metre outer canal, 188-metre rivetment and a 4.5-metre wide and 244-metre-long concrete bridge will be constructed.
The project also includes the construction of a ramp and the installation of canal lights.
The project is worth MVR 39.4 Million.