Maldives Transport and Contracting Company MTCC has announced the progress of the developmental projects it is undertaking in two islands.

In a tweet, MTCC said that work on the design and build of S. Meedhoo Harbour is well underway, with overall 80 percent project progress completed.

It said that channel dredging works and quay wall works for the project are currently ongoing, with 34 percent and 85 percent completion respectively.

MTCC added that the project was mobilized on 18th September 2019.

MTCC says the road construction project of R. Ungoofaaru is also going well/ Photo: MTCC

Meanwhile, the company said that the road construction project of R. Ungoofaaru is also going well, with overall 42 percent project progress achieved.

MTCC said that the installation of 2000sqm stormwater pipes has been completed and subgrade works have commenced.

It added that the project was mobilized on 12th June 2019.